@@ -3,14 +3,14 @@ gsd_state_version: 1.0
|
||||
milestone: v2.0
|
||||
milestone_name: Business Operations Suite
|
||||
status: executing
|
||||
last_updated: "2026-06-11T07:40:00Z"
|
||||
last_updated: "2026-06-11T19:00:00Z"
|
||||
last_activity: 2026-06-11
|
||||
progress:
|
||||
total_phases: 5
|
||||
completed_phases: 1
|
||||
total_plans: 8
|
||||
completed_plans: 5
|
||||
percent: 62.5
|
||||
completed_phases: 4
|
||||
total_plans: 11
|
||||
completed_plans: 11
|
||||
percent: 80
|
||||
---
|
||||
|
||||
# Project State
|
||||
@@ -23,10 +23,24 @@ See: .planning/PROJECT.md (updated 2026-05-09)
|
||||
|
||||
## Current Position
|
||||
|
||||
Phase: 09-quote-builder-client-acceptance (Plan 3 just completed)
|
||||
Plans: 07 (complete) | 08 (complete) | 09-01 (complete) | 09-02 (complete) | 09-03 (complete)
|
||||
Status: Phase 7 executed ✓ | Phase 8 executed ✓ | Phase 9 Plan 1-3 executed ✓
|
||||
Last activity: 2026-06-11T07:40:00Z — Phase 9 Plan 3 execution complete (public quote page with rate limiting)
|
||||
Phase: 10-crm-pipeline-activity-logging (redo complete, deployed)
|
||||
Plans: 07 (complete) | 08 (complete) | 09-01..03 (complete) | 10-01..03 (complete, redeployed 2026-06-11)
|
||||
Status: Phase 7 ✓ | Phase 8 ✓ | Phase 9 ✓ | Phase 10 ✓ (staged redo after rollback)
|
||||
Last activity: 2026-06-11T19:00:00Z — Phase 10 staged redo deployed; production DB migrations 0001/0003/0004/0005 applied
|
||||
|
||||
## What Was Built (Phase 10 — CRM Pipeline & Activity Logging, redo)
|
||||
|
||||
### Root cause of the original Phase 10 production crash (resolved)
|
||||
|
||||
Production Postgres (Coolify container) had **no migrations applied after 0000** — `services`, `leads`, `offer_phases`, `offer_phase_services`, `quotes` did not exist. Phase 7/8/9 summaries said "migration pending connectivity" and were never followed up. Any page querying those tables 500'd: catalog (services), quote builder + /quote/[token] (quotes), and after Phase 10 deploy also dashboard (FollowUpWidget → leads). The Phase 10 rollback only masked the dashboard symptom.
|
||||
|
||||
**Fix (2026-06-11):** migrations 0001+0003+0004+0005 applied atomically (single transaction, additive-only, verified zero DROP/TRUNCATE) via SSH → docker exec psql on container `xwkk0040w0kk0gsgcgog8owk`, db `clienthub`. Protected rows verified intact post-migration (4 clients, 5 projects, 13 payments, 6 phases). `/quote/[token]` 500 → 404 (correct behavior) confirmed.
|
||||
|
||||
### Delivered (redo commits 5aa6614 + 008a434)
|
||||
|
||||
- **Stage A** (`5aa6614`): deps `@radix-ui/react-dialog`, `date-fns` + shared `ui/dialog.tsx`, `ui/form.tsx`
|
||||
- **Stage B**: production DB schema aligned (see above) — script `scripts/push-phase10-migration.ts` for future reuse
|
||||
- **Stage C** (`008a434`): schema.ts CRM tables (leads expansion, activities, reminders + relations), lead-service/lead-validators, `/admin/leads` list+detail+actions, LeadTable/LeadDetail/LeadForm, LogActivityModal, SendQuoteModal, FollowUpWidget on dashboard, sidebar link
|
||||
|
||||
## What Was Built (Phase 9 — Quote Builder UI & Public Pages)
|
||||
|
||||
@@ -174,18 +188,18 @@ Last activity: 2026-06-11T07:40:00Z — Phase 9 Plan 3 execution complete (publi
|
||||
|
||||
## Session Continuity
|
||||
|
||||
Last session: 2026-06-11T07:40:00Z
|
||||
Phase 9 Plan 3 execution complete (Public quote page with rate limiting and multistep wizard).
|
||||
All quote builder infrastructure in place: validators, service layer, admin UI, public page.
|
||||
Ready for next plan: Phase 9 Plan 4 (Quote Items & Pricing Configuration).
|
||||
Last session: 2026-06-11T19:00:00Z
|
||||
Phase 10 staged redo complete: production DB migrations applied (0001/0003/0004/0005), CRM module deployed.
|
||||
Dangling work recovered from `phase10-wip` branch (anchor of reflog commit 8e2752a — branch can be deleted once redo verified in production).
|
||||
Lesson recorded: migrations are applied manually in this project — every deploy touching schema MUST apply the migration to prod BEFORE pushing code.
|
||||
|
||||
## Operator Next Steps
|
||||
|
||||
### Immediate (Phase 9 Remaining Plans)
|
||||
### Immediate
|
||||
|
||||
- Phase 9 Plan 4: Quote items configuration (admin can add/edit line items per phase)
|
||||
- Phase 9 Plan 5: Service picker and price overrides per line item
|
||||
- Phase 10: Email confirmation via Resend, quote expiration, sharing links
|
||||
- Verify in browser (authenticated): /admin (FollowUpWidget), /admin/leads, /admin/catalog, /admin/quotes/new
|
||||
- Re-run `/gsd-plan-phase 11` and `/gsd-plan-phase 12` (planning folders never committed, must be regenerated)
|
||||
- Optionally cherry-pick sidebar "App shortcuts" dangling commit 5d75752 if still wanted
|
||||
|
||||
### Phase 10 (Concurrent Activities)
|
||||
|
||||
|
||||