docs(state): update Phase 10 Plan 3 completion status
- Marked Phase 10 Plans 1-3 complete (100% Wave 1-2) - Updated progress: 6/8 plans complete (75%) - Updated timestamp: 2026-06-11T12:38:00Z - Added Phase 10 summary: CRM foundation, lead UI, activity logging and follow-up widget - All tasks verified: build passes, TypeScript checks pass, routes generated Co-Authored-By: Claude Haiku 4.5 <noreply@anthropic.com>
This commit is contained in:
+46
-8
@@ -3,14 +3,14 @@ gsd_state_version: 1.0
|
||||
milestone: v2.0
|
||||
milestone_name: Business Operations Suite
|
||||
status: executing
|
||||
last_updated: "2026-06-11T07:40:00Z"
|
||||
last_updated: "2026-06-11T12:38:00Z"
|
||||
last_activity: 2026-06-11
|
||||
progress:
|
||||
total_phases: 5
|
||||
completed_phases: 1
|
||||
completed_phases: 2
|
||||
total_plans: 8
|
||||
completed_plans: 5
|
||||
percent: 62.5
|
||||
completed_plans: 6
|
||||
percent: 75.0
|
||||
---
|
||||
|
||||
# Project State
|
||||
@@ -23,10 +23,10 @@ See: .planning/PROJECT.md (updated 2026-05-09)
|
||||
|
||||
## Current Position
|
||||
|
||||
Phase: 09-quote-builder-client-acceptance (Plan 3 just completed)
|
||||
Plans: 07 (complete) | 08 (complete) | 09-01 (complete) | 09-02 (complete) | 09-03 (complete)
|
||||
Status: Phase 7 executed ✓ | Phase 8 executed ✓ | Phase 9 Plan 1-3 executed ✓
|
||||
Last activity: 2026-06-11T07:40:00Z — Phase 9 Plan 3 execution complete (public quote page with rate limiting)
|
||||
Phase: 10-crm-pipeline-activity-logging (Plan 3 just completed)
|
||||
Plans: 07 (complete) | 08 (complete) | 09-01 (complete) | 09-02 (complete) | 09-03 (complete) | 10-01 (complete) | 10-02 (complete) | 10-03 (complete)
|
||||
Status: Phase 7 executed ✓ | Phase 8 executed ✓ | Phase 9 Plan 1-3 executed ✓ | Phase 10 Plan 1-3 executed ✓
|
||||
Last activity: 2026-06-11T12:38:00Z — Phase 10 Plan 3 execution complete (activity logging modals and follow-up widget)
|
||||
|
||||
## What Was Built (Phase 9 — Quote Builder UI & Public Pages)
|
||||
|
||||
@@ -72,6 +72,44 @@ Last activity: 2026-06-11T07:40:00Z — Phase 9 Plan 3 execution complete (publi
|
||||
- **Security:** quote_items never exposed; only accepted_total and phase summary visible to client
|
||||
- **Status:** DONE — Route visible in build output, 3 commits, all tests passing (npm run build: 0 errors)
|
||||
|
||||
## What Was Built (Phase 10 — CRM Pipeline & Activity Logging) ✓
|
||||
|
||||
### 10-01: CRM Foundation ✓
|
||||
|
||||
- **Schema:** leads, activities, reminders tables with proper relations and cascade delete
|
||||
- **TypeScript:** Lead, Activity, Reminder types exported from schema.ts
|
||||
- **Validators:** src/lib/lead-validators.ts with Zod schemas (createLeadSchema, createActivitySchema, createReminderSchema)
|
||||
- **Service Layer:** src/lib/lead-service.ts with 12+ query functions (getAllLeads, getLeadsNeedingFollowUp, createActivity, etc.)
|
||||
- **Status:** DONE — Foundation ready for UI integration
|
||||
- **Data Safety:** Schema-only changes, no data at risk
|
||||
|
||||
### 10-02: Lead Management UI ✓
|
||||
|
||||
- **Components:** LeadTable.tsx, LeadDetail.tsx, LeadForm.tsx (CreateLeadModal, EditLeadModal)
|
||||
- **Pages:** /admin/leads (list) and /admin/leads/[id] (detail) with activity log and reminders
|
||||
- **Server Actions:** createLead(), updateLead(), deleteLead() with Zod validation and revalidation
|
||||
- **Features:** Status badges (6 pipeline stages), activity history, upcoming reminders display
|
||||
- **Status:** DONE — Full CRUD interface operational
|
||||
- **Build:** npm run build passes with 0 errors
|
||||
|
||||
### 10-03: Activity Logging & Quote Sending ✓
|
||||
|
||||
- **LogActivityModal:** Component for registering activities (call/email/meeting/note)
|
||||
- Form with type selector, date picker, optional duration, notes textarea
|
||||
- Server action logActivity() auto-updates lead.last_contact_date
|
||||
- Revalidates lead detail page on success
|
||||
- **SendQuoteModal:** Two-tab modal for assigning quotes
|
||||
- Existing quote tab: paste token, submit links quote to lead
|
||||
- Create new tab: redirects to quote builder with lead_id param
|
||||
- Server action assignQuoteToLead() updates lead.status → "proposal_sent"
|
||||
- Validates quote token against database
|
||||
- **FollowUpWidget:** Dashboard card showing leads needing follow-up (>7 days no contact)
|
||||
- Displays count and top 3 leads with quick-access links
|
||||
- Orange-highlighted widget for visibility
|
||||
- Integrated into admin dashboard with Suspense boundary
|
||||
- **Status:** DONE — All modals, server actions, and widget operational
|
||||
- **Build:** npm run build passes with 0 TypeScript errors
|
||||
|
||||
## What Was Built (Phase 8 — Quote Builder Schema Foundation) ✓
|
||||
|
||||
### 08-01: Offer Phases & Quote Tables Schema ✓
|
||||
|
||||
Reference in New Issue
Block a user