simone e424653ece docs(11-03): complete EditableCell + TagMultiSelect plan
- add 11-03-SUMMARY.md documenting EditableCell/TagMultiSelect delivery
  and the react-hooks lint-rule fix (Rule 1 deviation)
- update STATE.md position (3 of 4 -> 4 of 4), progress 86% -> 89%,
  performance metrics, and decisions log
- log gsd-sdk unavailability and OFFER-07/08 status timing as deferred
  items for Phase 11
2026-06-13 15:56:06 +02:00

6.5 KiB

Deferred Items — Phase 11

Items discovered during execution that are out of scope for the current plan/task but logged for future cleanup.

From Plan 11-01

1. drizzle-kit generate non-functional (migration tooling drift)

  • Found during: 11-01, Task 1, step 5
  • Issue: src/db/migrations/meta/_journal.json and snapshot files are out of sync with schema.ts. Only meta/0000_snapshot.json exists; the journal has entries through 0001 only; SQL files 0003, 0004, 0005 (and now 0006, added in 11-01) were hand-written without corresponding journal entries or snapshots. Running npx drizzle-kit generate fails immediately with Error: Interactive prompts require a TTY terminal because drizzle-kit computes a huge diff against the stale 0000 snapshot.
  • Origin: Pre-existing since Phase 8 (commit f727954, "feat(08-02): create Phase 8 migration and validation script" — hand-wrote 0003_offer_phases_quote_templates.sql without updating journal/snapshots).
  • Impact: Every future migration in this repo must be hand-written following Drizzle's SQL output conventions (as 11-01 did for 0006_add_tags_table.sql) until snapshots are reconciled. Low risk as long as the convention is followed consistently, but increases manual effort and risk of SQL syntax drift from what Drizzle would generate.
  • Recommended fix: Architectural-scope task (Rule 4 — requires user decision): either (a) regenerate meta/*_snapshot.json files for 0001-0006 by introspecting the current live schema with drizzle-kit pull or manual reconstruction, or (b) accept hand-written migrations as the permanent convention and document it explicitly in CLAUDE.md/project docs so future agents don't attempt drizzle-kit generate and waste a turn on the TTY error.
  • Status: Not fixed. Logged only.

2. Stale quote_itemsservice_catalog JOIN in admin-queries.ts

  • Found during: 11-01 Task 2 (carried over from 11-CONTEXT.md "Claude's Discretion")
  • Issue: src/lib/admin-queries.ts (lines ~335/343 and ~531/539) does leftJoin(service_catalog, eq(quote_items.service_id, service_catalog.id)), but quote_items.service_id is typed as references(() => services.id, ...) (post-Phase-8). For quote_items rows created after Phase 8, this JOIN won't match and the label falls back to COALESCE(..., quote_items.custom_label), which may be null.
  • Impact: Low — admin-only label display in client/project workspace quote_items list. Non-blocking per 11-CONTEXT.md.
  • Recommended fix: 4-line change — replace leftJoin(service_catalog, ...) with leftJoin(services, eq(quote_items.service_id, services.id)) and service_catalog.name with services.name in both COALESCE expressions, at both line ranges.
  • Status: Not fixed. Candidate for Phase 12 cleanup or standalone hotfix.

3. .planning/ROADMAP.md is an empty placeholder for v2.1

  • Found during: 11-01 state-update step (gsd-sdk roadmap update-plan-progress 11)
  • Issue: .planning/ROADMAP.md contains only the literal text PLACEHOLDER (11 bytes). roadmap update-plan-progress 11 ran without error ("updated": true) but there is no "Phase 11" section to update, so the file content did not change. The real v2.1 roadmap content (referenced throughout 11-CONTEXT.md/STATE.md as "ROADMAP.md") does not exist in this file — only milestones/v1.0-ROADMAP.md and milestones/v2.0-ROADMAP.md exist.
  • Impact: Low for this plan (doesn't block 11-01 deliverables), but roadmap update-plan-progress is a no-op for the rest of v2.1 until this is fixed, and any future agent reading @.planning/ROADMAP.md for phase goals/success-criteria (as referenced in 11-CONTEXT.md canonical_refs) will find nothing.
  • Recommended fix: Populate .planning/ROADMAP.md with the v2.1 roadmap content (Phases 11-17), likely should have been written during /gsd-plan-phase v2.1 setup (commit 03898f2 "docs(planning): v2.1 milestone setup + Phase 11 context/patterns" added 11-CONTEXT.md/11-PATTERNS.md but apparently not ROADMAP.md body content).
  • Status: Not fixed — pre-existing planning-artifact gap, out of scope for this execution plan.

4. gsd-sdk CLI not available in 11-03 execution environment

  • Found during: 11-03, state-update step (init.execute-phase, state.advance-plan, roadmap.update-plan-progress, etc.)
  • Issue: gsd-sdk was not found on PATH, and no node_modules-installed copy or local CLI was discoverable. All state updates (STATE.md position/progress/metrics/decisions/session) for this plan were applied via direct Edit to .planning/STATE.md instead of via SDK query handlers. ROADMAP.md/REQUIREMENTS.md updates were skipped: ROADMAP.md is still the PLACEHOLDER (item #3 above, no Phase 11 section to update), and REQUIREMENTS.md already shows OFFER-07/OFFER-08 as "Complete" (marked during 11-02's execution, before this plan's UI work existed — see item #5).
  • Impact: Low for this plan — STATE.md was updated manually with equivalent content. No data loss. Future plans (11-04) should check gsd-sdk availability early and fall back to manual STATE.md edits if still missing.
  • Status: Not fixed — environment/tooling gap, out of scope for this execution plan.

5. OFFER-07/OFFER-08 marked "Complete" in REQUIREMENTS.md before their UI was built

  • Found during: 11-03, requirements-check step
  • Issue: .planning/REQUIREMENTS.md shows OFFER-07 ("L'utente vede ed edita il catalogo services come tabella con inline editing") and OFFER-08 (tag multi-select) as Complete, attributed to Phase 11 — but as of 11-02's completion, only the query layer + server actions existed (no UI). 11-03 (this plan) built the EditableCell/TagMultiSelect primitives, and 11-04 (not yet executed) is the plan that wires them into ServiceTable to deliver the actual user-facing inline-edit/tag UX described by OFFER-07/08.
  • Impact: Low — both requirements legitimately complete once 11-04 lands (this plan is a direct, immediate prerequisite, same wave sequence, no risk of the milestone closing prematurely mid-phase). However the "Complete" status in REQUIREMENTS.md was technically premature at the time 11-02 marked it.
  • Recommended fix: No action needed if 11-04 executes next as planned. If 11-04 is ever skipped/deferred, re-open OFFER-07/08 status in REQUIREMENTS.md to "In Progress" until the UI wiring lands.